| |
Construction
Company Home > Historic
Construction Projects > Construction of the Hoover Dam
Historic Construction Company Project - Hoover Dam
A Historical Outlook on its Construction
A
list of modern day construction projects that demonstrate
a construction company's ingenuity and creativity may very
well begin with The Hoover Dam.
The Hoover Dam was built by a construction company called
Six Companies Inc, which was actually a consortium of several
companies: Morrison-Knudsen Co., Utah Construction Co., J.
F. Shea Co., Pacific Bridge Co., MacDonald & Kahn Ltd.
and a joint venture of W. A. Bechtel Co., Henry J. Kaiser,
and Warren Brothers. The reason these construction companies
got together was simple: no single construction company could
raise the $5 million needed to secure the performance bond.
A number of construction companies were interested in the
job. After all, this was a historical project of great significance,
as well as an incredible challenge. It soon became obvious,
though, that no one company would be able to handle a project
of this magnitude. Even the very biggest construction companies
in that day had neither the capital nor the resources to take
on such a job.
Harry Morrison, president of Morrison-Knudson Co., approached
San Francisco banker Leland Cutler to seek financial backing
for Morrison-Knudsen Co. for the Hoover Dam project. Cutler
refused because he didn't think any one company could raise
the $5 million bond that was necessary, but he did give Morrison
the names of several other construction companies who might
be interested in a joint venture. Morrison quickly realized
the only way to get the Hoover Dam built was for several companies
to join together, and he organized the Six Companies consortium.
At that time, the leading dam builder in the United States
was Frank T. Crowe, a former Department of Reclamation superintendent.
Crowe had spent twenty years working for the Department of
Reclamation, as well as private construction companies. He
had helped to build Arrowrock Dam in Idaho, the Jackson Lake
Dam in Wyoming and Washington's Tieton Dam. Crowe had also
developed a cableway system of delivering concrete and moving
equipment that was far more advanced than any other system
of its time.
Everything Crowe had ever done during his career helped prepare
him for the building of Hoover Dam, which would be the biggest
challenge of his life. Crowe aided Reclamation Commissioner
Arthur Powell Davis in developing a cost estimate for a dam
on the lower Colorado River as early as 1919 and also helped
with the preliminary design in 1924.
Prior to 1925, when the Reclamation Service (which later
became the Department of Reclamation) wanted to build a dam,
the government did the project itself. In 1925, the government
began contracting such projects out. Frank Crowe wanted very
badly to work on the Hoover Dam; in fact, it had been a dream
of his for a very long time. And now that the Reclamation
Service had changed its way of doing business, Crowe had to
choose between staying in his government job or working on
the Hoover Dam. To work on off the Hoover Dam project, Crowe
would be forced to leave his job and team up with a construction
company. Crowe decided to join Morrison-Knudsen Co., and was
instrumental in persuading Morrison to organize Six Companies.
Since Crowe had two decades of experience and had worked
on the project's cost estimate for the government, he knew
what went into the calculations the government used to develop
their estimates. Morrison gathered together the construction
companies that would make up Six Companies, made Crowe construction
superintendent and won the contract on March 4, 1931. Six
Companies bid $48.9 million for the project, a bid that was
just $24,000 higher than the Department of the Interior had
budgeted for the project and $10 million lower than the next
lowest bid. At the time, this was the largest single contract
the United States government had ever awarded. In today's
dollars, that bid would be more than $577 million.
Six Companies Delivered Comprensive Construction Expertise
Each
member of the Six Companies consortium brought a special expertise
to the table. The Wattis Brothers of Utah Construction were
well known for their expertise in building the early railroads
in the western United States and Mexico. The JF Shea Company
had started out as a plumbing business and was experienced
in tunnel building and other underground work. Charles Shea
knew people at the Pacific Bridge Company, and he convinced
them to bring their expertise and capital to the project.
Felix Kahn of San Francisco's MacDonald and Kahn had built
a number of large buildings in San Francisco and contributed
$1 million to the project. Henry Kaiser and Warren Bechtel
were experienced in road building.
Word of the Hoover Dam project spread quickly, and Six Companies
quickly received more than 2,400 job applications and over
12,000 letters of inquiry about jobs. This was during the
Depression. Times were tough and many people desperately needed
work. Workers flocked to the building area from all over country,
more than 5,000 in all. Many brought their wives and children
and lived in tents. With poor sanitation, little access to
clean water, 119-degree heat and no utilities, this tent community
was a living hell. Six Companies realized that these people
would be here for years and something had to change. Along
with the Reclamation Service and under Frank Crowe's guidance,
Six Companies built Boulder City. Electricity was brought
in, and a school, churches, post office, library, newspaper
and stores were built.
Before construction on the dam could start, a monumental
task was at hand. The construction companies had to divert
the Colorado River away from the project's foundation site,
and this could only happen during the winter. Crowe decided
this needed to be done during the winter of 1932-33. Work
on the tunnels began in May 1931. For 24 hours a day, seven
days a week four tunnels, two on each side, were built right
through the rock walls of the canyon. Each tunnel was 4,000
feet long, 56 feet in diameter, and lined with three feet
of concrete, making them the second largest tunnels ever made.
The diversionary tunnels had to be built in the summer in
order to be ready to divert the river in the winter. Conditions
in the tunnels were brutal, with temperatures inside reaching
140 degrees Fahrenheit. As many as four workers died from
heat prostration each week. To make matters worse, Six Companies
used gasoline-powered trucks in the tunnel, something that
had never been done before in underground mining, so carbon
monoxide was added to the heat, dust, and fumes from the blasting.
Crowe was a mechanical genius, something he had proven time
and time again on his previous dam projects. He conceived
of many new inventions during the course of building Hoover
Dam, one of which occurred during the building of the diversionary
tunnels. He came up with a drilling jumbo, four platforms
welded to a truck that carried 30 rock drills. This enabled
construction workers to complete the tunnels and cofferdams
by April 1932, a full year ahead of schedule. Construction
on the dam base could now begin.
In
order for Six Companies to recover its initial $5 million
investment, it gave high prices for the work done in the diversion
phase and lower prices for subsequent work. But in order for
this to work, Frank Crowe had to place the 3.4 million cubic
yards of concrete necessary to complete the dam for only $2.70
per yard, a price that was 35% lower than the price of the
second lowest bidder. Further, Six Companies had agreed to
a $3,000 per day penalty for every day the project went over
schedule, so it was imperative that everything go according
to plan. Crowe overcame these challenges magnificently. Not
only was he able to get the concrete into place at the right
price, he also did it ahead of schedule.
The base of the Hoover Dam, as with any dam, was the most
important part of the structure. If the base wasn't built
correctly, to there could be numerous potential problems with
the rest of the structure. Construction workers had to use
power shovels to dig through more than half-million cubic
yards of river bottom mud to reach the bedrock 40 feet below,
making the total excavation 125 feet, with grouting as deep
as 150 feet. Simultaneously, high scalers blasted the canyon
walls with jackhammers to make a smooth surface for the dam's
construction. These scalers earned $5.60 a day and were some
of the highest paid workers on the job.
On June 6, 1933, two years after Six Companies won the contract,
they started pouring the concrete for the dam's base. In order
to allow the concrete to dry properly and not crack during
the process, construction workers had to pour 230 individual
blocks of concrete for the base. All in all, 3.25 million
cubic yards of concrete were used for the base, enough concrete
to pave a highway 16 feet wide from New York to San Francisco.
The first eight-cubic-yard bottom-dump bucket of concrete
went into the dam 18 months ahead of schedule. The dam's great
mass of concrete was stripped of heat by pumping refrigerated
water through 590 miles of pipe placed in the concrete as
it was poured. The four 395-foot intake towers were taller
than most buildings. The powerhouse's two 230-foot-high wings
were designed to house 17 generating units. When construction
was complete in 1935, the diversionary tunnels were closed,
and the filling of Lake Mead began.
The Construction Project Completed
All
in all, Hoover Dam stood 725 feet high, is 1244 feet wide,
660 feet thick at the base, tapering to a thickness of 45
feet at the top. It cost a total of $165 million to build
and was completed in four and a half years. The project was
begun in March 1931 and President Franklin D. Roosevelt dedicated
it on September 30, 1935. First power was produced in October
1936, more than two years ahead of schedule. A total of 4.4
million yards of concrete were used in its construction. The
powerhouse used 17 generators in 10 acres of floor space to
produce over 4 billion kilowatt-hours for California, Nevada,
and Arizona.
The name of the dam has changed several times. Early in the
construction process, surveyors thought the dam should be
built at Boulder Canyon because of its granite floor, and
the dam was to be called Boulder Dam. It was later determined
that Black Canyon was a more suitable site since a dam in
this location would not have to be quite as high, but the
name was left as Boulder Dam. During the strike-driving ceremony
on September 17, 1930, Secretary of the Interior Ray L. Wilbur
named the dam Hoover Dam in honor of President Herbert Hoover,
which came as a great surprise to everyone. In 1933 voters
elected Democrat Franklin D. Roosevelt as president, and his
Secretary of the Interior Harold Ickes changed the name back
to Boulder Dam. Fourteen years later, a joint resolution of
Congress changed the name back to Hoover Dam.
Six Companies accomplished a historic feat, working together
to build the Hoover Dam. The construction companies that made
up the consortium went their separate ways after the Hoover
Dam project, and accomplished a variety of successful projects
afterwards.
- Morrison-Knudsen Company president Henry Morrison appeared
on the cover of Time Magazine in 1954, his company
having grown to one of the largest construction and engineering
companies in the world. The company was involved with many
construction projects, including the Trans-Alaska pipeline.
Morrison died in 1971. In 1996 Morrison-Knudesen Company
was acquired by Washington Group International.
- The Utah Construction Company diversified into commercial,
residential and military construction, as well as mining,
in the 1950s. The company changed its name in 1971 to Utah
International, Inc. and entered into a $2.3 billion merger
with General Electric in 1976.
- J.F. Shea helped to build the Grand Coulee Dam, the Golden
Gate Bridge, the San Francisco Bay Area Rapid Transit system
and the Washington, D.C., subway system. The company is
still in business today. It builds planned communities and
is a civil engineering, electrical and construction contractor,
as well as a supplier of aggregate materials to contractors.
The company also manufactures concrete-placing equipment
for civil engineering projects.
- The Pacific Bridge Company went back to building bridges,
including the Tacoma Narrows Bridges. The company also worked
with Morrison-Knudsen Company on the salvage project after
the bombing of Pearl Harbor.
- Bechtel has completed more than 22,000 projects in 140
countries, including the Channel Tunnel, Hong Kong International
Airport, the San Francisco Bay Area Rapid Transit (BART)
system and the reconstruction of Kuwait's oil fields after
the Gulf War.
- Henry Kaiser worked on the Grand Coulee Dam and the San
Francisco Bay Bridge. In 1939 he founded Permanente, the
largest cement plant in the world and joined with Todd Shipbuilding
Co. to build ships for the Merchant Marines.
- Warren Brothers Paving, who had built the first modern
asphalt facility in 1901 went on to pave the Columbia River
highway and worked on the Walden Pond demonstration project.
And what happened to Frank Crowe, the superintendent for
the Hoover Dam project? He made a $350,000 bonus at the completion
of the Hoover Dam. After that he went on to build four more
dams in his life, but no other project would match the scale
and impact of the Hoover Dam.
|